abb
Corsica Prunu PV project officially connected to EDF/SEI Corsican grid, production has started.
The 4,5 MW project managed by The meeco Group in coordination with So/Lar Corse, ABB and Ralos has been successfully connected to the Corsican grid. Last Monday 29th November, the official “Mise en service industrielle” notification from EDF was communicated with the first kilowatts flowing into the grid on that same day. With the official … Read more
Corsica Prunu PV project officially accepted by the French CONSUEL
The 4,5 MW project managed by meeco AG in coordination with So/Lar Corse, ABB and Ralos has been officially approved by the CONSUEL – French association delivering the compliance visa with national electrical standards. “The approval process with the CONSUEL was positively short” explains Laurent Dittrick, in charge of Project Development for So/Lar Corse. “We … Read more
meeco’s 4,5 MWp Prunu project completed – Final positive outcome will be reached within next few days
Thanks to the professionalism and dedication of all actors, meeco AG is very proud to announce the successful ending of construction work of the Prunu PV plant project on Friday, 26th, August 2011. Whilst meeco AG has been responsible for the entire project management, the 4500 kWp project has been realized in close and fruitful … Read more